5 Land Development La Perle du Lac 2 subdivision
• During 2022, efforts were focused on the completion of the detailed studies, the preparation
During 2022, the company continued actively, its regular activity; with the adjacent to the major water platform. The completion rate up to the end of
of provisional and final bid request and their validation by the relevant public authorities.
completion of some supplementary work at the level of la Perle du Lac 1 the year was about 32 %.
• Also, on December 20, 2022, a consultation was issued to the contracting companies that were
subdivision. On the other hand, it continued working to obtain the approval for • Another direct agreement has also been concluded with the Libyan Arab-
selected within the framework of the initial request for offers to select contractors or contracting
la Perle du Lac 2 subdivision and Les villas subdivision, and also preparing for Tunisian Consultancy firm to carry out the monitoring and following up the
groups to complete the work of development of la Perle du Lac 2 subdivision, and a request for proposals
the launch of studies for la Perle du Lac subdivisions 3 and 4. Thanks to the supplementary preparation work ;
was issued to choose a consultancy firm to follow up on these works.
sustained work with the municipality services, the company was able to obtain • The construction of an underground parking lot for cars has been
• These works will be completed during the first semester of 2023.
the approval for the subdivision la Perle du Lac 2 on December 16, 2022. completed, with a total area of about 5.000 square meters ;
• Within the framework of the same deal, 3 water platforms have been
The Perle du Lac 1 subdivision completed, including a large platform (with an area of about 2.200 m²) that
will be allocated for picnics, cultural events, celebrations as well as urban
• In 2022, a deal was concluded with the «Bouzghenda Frères» contractor furnishing of the squares and the promenade.
to carry out work off the underground shelter and at the corniche level
26 27